Delivery work

Six delivery case studies

Each one follows the same pattern: problem, role, actions, result, evidence. Expand any card for the full artefacts and evidence.

AuditFlow OS, the flagship product build, has its own page. View AuditFlow OS →

Some cards include an illustrative artefact preview. Original evidence and records from HMG and Lewisham Homes cannot be shared, so these are generic recreations built to show structure, not real project documents.
Audit & assurance

1. HMG IS4 Audit Readiness & COMSEC Audits

HMG · COMSEC Compliance Team

Role
Auditor / Incident Manager
Project type
Audit & assurance
Environment
Government, multiple concurrent accounts
Duration
Nov 2025 to Jun 2026

Problem

Government and regulated organisations have to demonstrate HMG IS4 v8.1 compliance for cryptographic custodianship, but audits run across multiple accounts at once, and evidence and audit trails are often scattered across teams and inconsistently documented, so fieldwork has to be scheduled without slowing down any single engagement.

Actions

  • Built one structured audit readiness pack used across all accounts, rather than tailoring evidence frameworks separately for each one
  • Coordinated evidence review and fieldwork scheduling across multiple concurrent audit accounts with auditee contacts
  • Reviewed accounting records, permission logs and authorisation documentation against information assurance requirements to determine audit-trail completeness
  • Applied risk assessment methodology to produce risk-rated findings, then briefed senior stakeholders and tracked remediation to closure
  • Investigated cryptographic incidents from initial escalation through root-cause analysis, corrective action planning and validation
Scope & Plan
Request Evidence
Review & Validate
Findings & Risk Rating
Remediation

Result

Risk-rated findings with remediation actions
Clear, evidence-based conclusions
Non-compliance tracked through to closure

Lesson: a defensible finding depends on evidence that is traceable back to a control, not just a narrative description of what was seen.

Evidence

Audit readiness packEvidence request trackerFindings registerRisk rating matrixRemediation tracker

Illustrative

Findings register (structure only)

RefControl areaFindingRatingStatus
F-01Access controlPeriodic access review not evidencedHighOpen
F-02Change managementChange record missing approval sign-offMediumIn progress
F-03DocumentationProcedure document out of dateLowClosed

Illustrative recreation, not an actual HMG document.

Risk identification & mitigationGovernance & complianceProcess mapping

Service transformation

2. Service Request Catalogue & Onboarding Transformation

HMG · ServiceNow & Service Manager

Role
Service Request Catalogue Analyst
Project type
Service transformation
Environment
Secure service, office & remote routes
Duration
Feb 2022 to Nov 2025

Problem

New starters were delayed because the request process was fragmented: office-based and remote onboarding ran through separate approval routes, approvals were not always clear, and any redesign had to work for both without creating two systems to maintain.

Actions

  • Consolidated approval workflows into a single request journey instead of optimising each route separately
  • Redesigned request forms, workflow logic and approval routes, then tested them before release
  • Audited 200+ catalogue offerings three times a year and created/tested 20+ self-service catalogue offerings
  • Analysed 11 months of service desk data to identify and fix routing failures
Request Intake
Approval Routing
Fulfilment & Delivery
Closure & Feedback

Result

Before

2–3 months

After

<1 month

Lesson: onboarding issues are often workflow issues, not just fulfilment issues. Ownership has to be visible before a request goes live.

Evidence

Workflow mapApproval matrixRequest form design notesTest scriptsRelease checklist

Illustrative

Onboarding approval workflow (structure only)

  1. Request submitted by new starter or line manager, single form for office and remote routes
  2. Line manager approval confirms role, start date and equipment needs
  3. Security & governance check validates access level against role
  4. Routed to resolver group for fulfilment: accounts, equipment, access
  5. Closure & feedback confirms request complete and starter is ready

Illustrative recreation, not an actual HMG workflow diagram.

Stakeholder engagementUAT & workflow testingGovernance & complianceProcess mapping

Digital delivery

3. Housing Inspection Digitisation

Lewisham Homes · includes Surface Pro deployment

Role
Infrastructure Support Officer, IT representative
Project type
Digital delivery
Environment
Public sector, field & office
Duration
Oct 2020 to Feb 2022

Problem

Housing inspections ran on paper-heavy, manual processes. Field connectivity could not be guaranteed, so the technology choice had to work in inconsistent network conditions, not just ideal test conditions.

Actions

  • Recommended Surface Pro devices with Citrix and mobile data connectivity, based on operational risk assessment rather than device specification alone
  • Advised IT leadership on technology options and implementation risk, and coordinated with field teams, suppliers and the service desk on rollout risk
  • Supported deployment and adoption of 150 to 200 devices, enabling on-site data capture and digital signatures
  • Supported user training and change adoption through the rollout
Business Need
Solution Definition
Pilot & Testing
Deployment
Adoption

Result

150–200 devices deployed
Manual re-entry reduced
Faster turnaround, better data accuracy

Lesson: field technology has to be designed around the real working environment; selection should weigh operational risk, not only device features.

Evidence

Technology risk assessmentDevice rollout planInspection workflow diagramUser training notes

Illustrative

Surface Pro rollout checklist (structure only)

  • Device imaged and configured with Citrix and mobile data profile
  • Connectivity tested in a representative field location
  • Digital signature capture confirmed on-site
  • User training completed and support contact issued
  • Device handed over and inspection record created

Illustrative recreation, not an actual Lewisham Homes document.

Risk identification & mitigationRollout & change managementDelivery management

Infrastructure delivery

4. Remote Working Enablement

Lewisham Homes · COVID laptop rollout

Role
Infrastructure Support Officer
Project type
Infrastructure delivery
Environment
Public sector, lockdown response
Duration
2020, COVID lockdown period

Problem

Lockdown required a fast move to remote working. Devices had to reach staff and be secured for remote access in a much shorter timeframe than a normal rollout, without the usual lead time to test everything end to end.

Actions

  • Built access provisioning and endpoint controls into the deployment process itself, prioritising secure-by-default over speed alone
  • Led device preparation and dispatch for 250+ laptops
  • Coordinated access provisioning across Active Directory, Intune and MobileIron, and set up Citrix for secure remote access
  • Maintained business continuity through operational disruption, alongside continued infrastructure delivery for hybrid working and office downsizing
Plan
Configure
Deploy
Secure Access
Support

Result

250+ laptops deployed
Access controls maintained at scale
Remote working enabled without service loss

Lesson: rapid rollout only holds up if access provisioning and endpoint controls are built in from the start rather than added afterwards.

Evidence

Device deployment checklistAccess provisioning logSupport runbook

Illustrative

Lockdown deployment plan (structure only)

Week 1 — Prioritise dispatch by role, image and configure first batch of laptops
Week 2 — Provision access in Active Directory, Intune and MobileIron as devices go out
Week 3 — Set up Citrix remote access, monitor early support demand
Ongoing — Run support desk for access issues, track outstanding device requests to closure

Illustrative recreation, not an actual Lewisham Homes document.

Rollout & change managementDelivery management

Cost optimisation

5. Telecom Estate Rationalisation

Lewisham Homes · migration to O2

Role
Infrastructure Support Officer
Project type
Cost optimisation
Environment
Public sector IT
Duration
During O2 migration

Problem

The business SIM estate had grown without regular review. A migration to O2 was an opportunity to check which lines were still active before carrying them across, but the migration could not interrupt active users, so every recommendation had to be validated first.

Actions

  • Led a SIM usage audit across the business estate, collecting and analysing usage data line by line
  • Recommended removing dormant and duplicate SIMs during migration rather than carrying unnecessary assets into the new contract
  • Coordinated recommendations with service owners and finance before any lines were switched off
  • Delivered SIM deactivation as part of the O2 migration
Data Collection
SIM Audit
Stakeholder Discussions
Recommendation
Implementation

Result

Operational220 → 117 active SIMs
Cleaner, auditable telecom estate
BusinessEstimated 30% telecom cost reduction
Reduced unnecessary contract spend

Lesson: a migration is the natural point to audit an estate, since the business already has to touch every line to move it.

Evidence

SIM usage audit logStakeholder recommendation memoMigration trackerCost savings summary

Illustrative

SIM usage audit summary (structure only)

SIM rangeUsageRecommendation
***1200–1234No activity, 90+ daysDeactivate
***1235–1260Duplicate of active lineDeactivate
***1261–1289Low, seasonal useReview
***1290–1340Regular business useRetain

Illustrative recreation, not an actual Lewisham Homes document.

Governance & complianceRisk identification & mitigationDelivery management

Learning design

6. New Member Experience & Knowledge Transfer

HMG · COMSEC Compliance Team · sanitised summary

Role
Onboarding & training design lead
Project type
Learning design & knowledge transfer
Environment
Government audit team, sanitised summary
Duration
Nov 2025 to Jun 2026, as new members joined

Problem

New members needed enough framework knowledge to be useful quickly, but audit work is high-stakes, so onboarding had to build real competence, not just familiarity, before anyone touched live compliance work. All operationally sensitive detail and security markings have been removed from this summary.

Actions

  • Sequenced the path so shadowing live audit activity came after custodian training and documentation grounding, so new members had context for what they were watching
  • Designed the onboarding curriculum and training sequence
  • Delivered custodian training and audit documentation walkthroughs
  • Coordinated shadowing on live audit activity and built practical confidence before independent compliance work
Framework Understanding
Custodian Training
Documentation
Shadowing
Confidence Building

Result

Structured path from theory to live audit shadowing
Faster ramp-up for new team members
Reusable onboarding structure for future joiners

Lesson: this shows I can turn technical subject matter into a structured onboarding journey, not just deliver the work myself.

Evidence

Onboarding curriculum outlineCustodian training notesShadowing schedule

Illustrative

Onboarding ownership grid (structure only)

ActivityResponsibleAccountableConsulted
Framework understandingNew memberTeam leadOnboarding lead
Custodian trainingOnboarding leadTeam leadNew member
Shadowing live auditsNew memberOnboarding leadSenior auditor
Sign-off to independent workTeam leadTeam leadOnboarding lead

Illustrative recreation, not an actual HMG document.

Delivery managementGovernance & compliance

Project archive

Five shorter case studies

Missed Call & Contact Driver Analysis

Analysed 11 months of missed call and service desk data to identify high-volume contact drivers, peak demand periods and routing failures across password resets, account lockouts and access queries.

SRC Conformance Audits

Conducted Service Manager conformance audits three times a year, reviewing 200+ catalogue offerings to verify ownership, points of contact, approval routes and SRC governance compliance.

Office Downsizing & Agile Workstation Rollout

Delivered infrastructure for hybrid working and office downsizing, including agile workstations, desk booking, authentication controls, network ports, server connectivity and workstation access.

SRC Glossary & Team Mentoring

Mentored three colleagues across an eight-person team in SRC processes and ITIL v4 preparation, and produced a 50+ term SRC glossary for new entrants.

AuditFlow OS Roadmap & Backlog

Phased roadmap running from Notion MVP through to SaaS scale, with a prioritised backlog covering audit records, findings, evidence, actions, dashboard and framework mapping. See the full AuditFlow OS page for details.

How I run delivery day to day

Project delivery toolkit

RAID

Risks, assumptions, issues and dependencies tracked through delivery.

RACI

Clear ownership: who is responsible, accountable, consulted and informed.

Workflow mapping

Current-state and target-state process maps.

UAT

User acceptance testing before release.

Rollout planning

Sequenced deployment, communication and support plan.

Lessons learned

Captured after each phase and fed into the next project.

Benefits tracking

Outcomes measured against the original objective.

Tools & Technologies

ServiceNowService ManagerPowerShellActive DirectoryMicrosoft IntuneMobileIronPower BIJiraConfluence

10+

Years across government & regulated environments

200+

Catalogue offerings audited yearly

150–200

Devices deployed, field rollout

25%

Reduction in system downtime