Six delivery case studies
Each one follows the same pattern: problem, role, actions, result, evidence. Expand any card for the full artefacts and evidence.
AuditFlow OS, the flagship product build, has its own page. View AuditFlow OS →
Audit & assurance1. HMG IS4 Audit Readiness & COMSEC Audits
HMG · COMSEC Compliance Team
- Role
- Auditor / Incident Manager
- Project type
- Audit & assurance
- Environment
- Government, multiple concurrent accounts
- Duration
- Nov 2025 to Jun 2026
Problem
Government and regulated organisations have to demonstrate HMG IS4 v8.1 compliance for cryptographic custodianship, but audits run across multiple accounts at once, and evidence and audit trails are often scattered across teams and inconsistently documented, so fieldwork has to be scheduled without slowing down any single engagement.
Actions
- Built one structured audit readiness pack used across all accounts, rather than tailoring evidence frameworks separately for each one
- Coordinated evidence review and fieldwork scheduling across multiple concurrent audit accounts with auditee contacts
- Reviewed accounting records, permission logs and authorisation documentation against information assurance requirements to determine audit-trail completeness
- Applied risk assessment methodology to produce risk-rated findings, then briefed senior stakeholders and tracked remediation to closure
- Investigated cryptographic incidents from initial escalation through root-cause analysis, corrective action planning and validation
Result
Lesson: a defensible finding depends on evidence that is traceable back to a control, not just a narrative description of what was seen.
Evidence
Audit readiness packEvidence request trackerFindings registerRisk rating matrixRemediation tracker
Findings register (structure only)
| Ref | Control area | Finding | Rating | Status |
|---|---|---|---|---|
| F-01 | Access control | Periodic access review not evidenced | High | Open |
| F-02 | Change management | Change record missing approval sign-off | Medium | In progress |
| F-03 | Documentation | Procedure document out of date | Low | Closed |
Illustrative recreation, not an actual HMG document.
Risk identification & mitigationGovernance & complianceProcess mapping
Service transformation2. Service Request Catalogue & Onboarding Transformation
HMG · ServiceNow & Service Manager
- Role
- Service Request Catalogue Analyst
- Project type
- Service transformation
- Environment
- Secure service, office & remote routes
- Duration
- Feb 2022 to Nov 2025
Problem
New starters were delayed because the request process was fragmented: office-based and remote onboarding ran through separate approval routes, approvals were not always clear, and any redesign had to work for both without creating two systems to maintain.
Actions
- Consolidated approval workflows into a single request journey instead of optimising each route separately
- Redesigned request forms, workflow logic and approval routes, then tested them before release
- Audited 200+ catalogue offerings three times a year and created/tested 20+ self-service catalogue offerings
- Analysed 11 months of service desk data to identify and fix routing failures
Result
2–3 months
<1 month
Lesson: onboarding issues are often workflow issues, not just fulfilment issues. Ownership has to be visible before a request goes live.
Evidence
Workflow mapApproval matrixRequest form design notesTest scriptsRelease checklist
Onboarding approval workflow (structure only)
- Request submitted by new starter or line manager, single form for office and remote routes
- Line manager approval confirms role, start date and equipment needs
- Security & governance check validates access level against role
- Routed to resolver group for fulfilment: accounts, equipment, access
- Closure & feedback confirms request complete and starter is ready
Illustrative recreation, not an actual HMG workflow diagram.
Stakeholder engagementUAT & workflow testingGovernance & complianceProcess mapping
Digital delivery3. Housing Inspection Digitisation
Lewisham Homes · includes Surface Pro deployment
- Role
- Infrastructure Support Officer, IT representative
- Project type
- Digital delivery
- Environment
- Public sector, field & office
- Duration
- Oct 2020 to Feb 2022
Problem
Housing inspections ran on paper-heavy, manual processes. Field connectivity could not be guaranteed, so the technology choice had to work in inconsistent network conditions, not just ideal test conditions.
Actions
- Recommended Surface Pro devices with Citrix and mobile data connectivity, based on operational risk assessment rather than device specification alone
- Advised IT leadership on technology options and implementation risk, and coordinated with field teams, suppliers and the service desk on rollout risk
- Supported deployment and adoption of 150 to 200 devices, enabling on-site data capture and digital signatures
- Supported user training and change adoption through the rollout
Result
Lesson: field technology has to be designed around the real working environment; selection should weigh operational risk, not only device features.
Evidence
Technology risk assessmentDevice rollout planInspection workflow diagramUser training notes
Surface Pro rollout checklist (structure only)
- Device imaged and configured with Citrix and mobile data profile
- Connectivity tested in a representative field location
- Digital signature capture confirmed on-site
- User training completed and support contact issued
- Device handed over and inspection record created
Illustrative recreation, not an actual Lewisham Homes document.
Risk identification & mitigationRollout & change managementDelivery management
Infrastructure delivery4. Remote Working Enablement
Lewisham Homes · COVID laptop rollout
- Role
- Infrastructure Support Officer
- Project type
- Infrastructure delivery
- Environment
- Public sector, lockdown response
- Duration
- 2020, COVID lockdown period
Problem
Lockdown required a fast move to remote working. Devices had to reach staff and be secured for remote access in a much shorter timeframe than a normal rollout, without the usual lead time to test everything end to end.
Actions
- Built access provisioning and endpoint controls into the deployment process itself, prioritising secure-by-default over speed alone
- Led device preparation and dispatch for 250+ laptops
- Coordinated access provisioning across Active Directory, Intune and MobileIron, and set up Citrix for secure remote access
- Maintained business continuity through operational disruption, alongside continued infrastructure delivery for hybrid working and office downsizing
Result
Lesson: rapid rollout only holds up if access provisioning and endpoint controls are built in from the start rather than added afterwards.
Evidence
Device deployment checklistAccess provisioning logSupport runbook
Lockdown deployment plan (structure only)
Week 1 — Prioritise dispatch by role, image and configure first batch of laptops
Week 2 — Provision access in Active Directory, Intune and MobileIron as devices go out
Week 3 — Set up Citrix remote access, monitor early support demand
Ongoing — Run support desk for access issues, track outstanding device requests to closure
Illustrative recreation, not an actual Lewisham Homes document.
Rollout & change managementDelivery management
Cost optimisation5. Telecom Estate Rationalisation
Lewisham Homes · migration to O2
- Role
- Infrastructure Support Officer
- Project type
- Cost optimisation
- Environment
- Public sector IT
- Duration
- During O2 migration
Problem
The business SIM estate had grown without regular review. A migration to O2 was an opportunity to check which lines were still active before carrying them across, but the migration could not interrupt active users, so every recommendation had to be validated first.
Actions
- Led a SIM usage audit across the business estate, collecting and analysing usage data line by line
- Recommended removing dormant and duplicate SIMs during migration rather than carrying unnecessary assets into the new contract
- Coordinated recommendations with service owners and finance before any lines were switched off
- Delivered SIM deactivation as part of the O2 migration
Result
Cleaner, auditable telecom estate
Reduced unnecessary contract spend
Lesson: a migration is the natural point to audit an estate, since the business already has to touch every line to move it.
Evidence
SIM usage audit logStakeholder recommendation memoMigration trackerCost savings summary
SIM usage audit summary (structure only)
| SIM range | Usage | Recommendation |
|---|---|---|
| ***1200–1234 | No activity, 90+ days | Deactivate |
| ***1235–1260 | Duplicate of active line | Deactivate |
| ***1261–1289 | Low, seasonal use | Review |
| ***1290–1340 | Regular business use | Retain |
Illustrative recreation, not an actual Lewisham Homes document.
Governance & complianceRisk identification & mitigationDelivery management
Learning design6. New Member Experience & Knowledge Transfer
HMG · COMSEC Compliance Team · sanitised summary
- Role
- Onboarding & training design lead
- Project type
- Learning design & knowledge transfer
- Environment
- Government audit team, sanitised summary
- Duration
- Nov 2025 to Jun 2026, as new members joined
Problem
New members needed enough framework knowledge to be useful quickly, but audit work is high-stakes, so onboarding had to build real competence, not just familiarity, before anyone touched live compliance work. All operationally sensitive detail and security markings have been removed from this summary.
Actions
- Sequenced the path so shadowing live audit activity came after custodian training and documentation grounding, so new members had context for what they were watching
- Designed the onboarding curriculum and training sequence
- Delivered custodian training and audit documentation walkthroughs
- Coordinated shadowing on live audit activity and built practical confidence before independent compliance work
Result
Lesson: this shows I can turn technical subject matter into a structured onboarding journey, not just deliver the work myself.
Evidence
Onboarding curriculum outlineCustodian training notesShadowing schedule
Onboarding ownership grid (structure only)
| Activity | Responsible | Accountable | Consulted |
|---|---|---|---|
| Framework understanding | New member | Team lead | Onboarding lead |
| Custodian training | Onboarding lead | Team lead | New member |
| Shadowing live audits | New member | Onboarding lead | Senior auditor |
| Sign-off to independent work | Team lead | Team lead | Onboarding lead |
Illustrative recreation, not an actual HMG document.
Delivery managementGovernance & compliance
Five shorter case studies
Missed Call & Contact Driver Analysis
Analysed 11 months of missed call and service desk data to identify high-volume contact drivers, peak demand periods and routing failures across password resets, account lockouts and access queries.
SRC Conformance Audits
Conducted Service Manager conformance audits three times a year, reviewing 200+ catalogue offerings to verify ownership, points of contact, approval routes and SRC governance compliance.
Office Downsizing & Agile Workstation Rollout
Delivered infrastructure for hybrid working and office downsizing, including agile workstations, desk booking, authentication controls, network ports, server connectivity and workstation access.
SRC Glossary & Team Mentoring
Mentored three colleagues across an eight-person team in SRC processes and ITIL v4 preparation, and produced a 50+ term SRC glossary for new entrants.
AuditFlow OS Roadmap & Backlog
Phased roadmap running from Notion MVP through to SaaS scale, with a prioritised backlog covering audit records, findings, evidence, actions, dashboard and framework mapping. See the full AuditFlow OS page for details.
Project delivery toolkit
RAID
Risks, assumptions, issues and dependencies tracked through delivery.
RACI
Clear ownership: who is responsible, accountable, consulted and informed.
Workflow mapping
Current-state and target-state process maps.
UAT
User acceptance testing before release.
Rollout planning
Sequenced deployment, communication and support plan.
Lessons learned
Captured after each phase and fed into the next project.
Benefits tracking
Outcomes measured against the original objective.
Tools & Technologies
ServiceNowService ManagerPowerShellActive DirectoryMicrosoft IntuneMobileIronPower BIJiraConfluence
10+
Years across government & regulated environments
200+
Catalogue offerings audited yearly
150–200
Devices deployed, field rollout
25%
Reduction in system downtime
Open to Roles Such As
Project ManagerTechnical Project ManagerInfrastructure Project ManagerDigital Delivery ManagerService Delivery ManagerPMO AnalystTransformation Analyst